March Progress
15.2%
Wing A:Â
Overview: Work undertaken until the month of January included concreting of second floor slab.
GF retail masonry work completed. FF level retail masonry work started.
15.75%
Wing B:Â
Overview: Work undertaken until the month of January included completion of column casting
for 3 rd floor level.
GF retail masonry work completed. FF level retail masonry work started.
19.25%
Wing C:Â
Overview: Work undertaken until the month of January included completion of 5 th floor column
casting.
Shuttering for 5 th floor slab is ongoing.
Masonry work completed for GF & FF retail units. 2 nd floor masonry work ongoing.
25.49%
Wing D:Â
Overview: Work undertaken until the month of January included completion of slab casting for
5 th floor.
Column casting ongoing for 6 th floor level.
Masonry work at 2nd floor level is completed. Masonry work for 3rd floor is ongoing.