Waghodia, Vadodara
Current Projects
Price On Call
Elite 3BHK Apartments & Shops
March Progress
15.9%
Wing A:Â
Overview: Work undertaken until the month of April included concreting of fifth floor columns.
Masonry work for the 1 st floor residential units was completed.
16.75%
Wing B:Â
Overview: Work undertaken until the month of April included concreting of fifth floor columns.
Slab shuttering work for 5 th floor slab has started.
Masonry work for the 1 st floor residential units was completed.
20.50%
Wing C:Â
Overview: Work undertaken until the month of April included concreting of eight floor columns.
Slab shuttering work for 8 th floor slab has started.
Electrical work for 1 st & 2 nd floor residential units was completed.
27.60%
Wing D:Â
Overview: Work undertaken until the month of April included masonry work for 7 th & terrace
parapet wall.
Electrical work for 3 rd & 4 th floor residential units was completed. Same for 5 th floor residential
units is ongoing.
In-unit plasterwork FF residential units was completed.
Plumbing work for FF residential units is ongoing.